New Endress+Hauser DP on a closed tank. Vendor drawing shows a wet leg. Ops filled it dry. Transmitter 4 mA is sitting 8% high. Before I drain a tank, what is the clean first cal you actually run in the field?
On-site nationwide · Legacy and current platforms
On-site nationwide
Plant floor
Imani Cole · Instrument tech
New Endress+Hauser DP on a closed tank. Vendor drawing shows a wet leg. Ops filled it dry. Transmitter 4 mA is sitting 8% high. Before I drain a tank, what is the clean first cal you actually run in the field?
Hank Dietrich · I&C
Don't drain the tank. Isolate, vent, fill the wet leg with the process fluid or glycol per the spec, then zero at empty-equivalent. 8% high on a dry install is the missing column. After that, one known-level check with a tape. Write the LRV/URV in the transmitter, not only in the DCS.